Schedule

Submit Civil Drawing to Orange Cty: November, 2006
Submit Full Drawings to Orange Cty: December, 2006
Drawings returned from Orange Cty: April, 2007
Sitework to begin: January, 2007
Construction to begin: August, 2007
Electrical, Plumbing, HVAC completed by March, 2008
Interior framing, electrical, plumbing and HVAC rough-in: April, 2007
Exterior painting: April, 2008
Walls up and roof by April, 2007
Drywall, trim, interior doors, painting: June, 2007
Parking lot, sod and landscaping completed by July, 2008
FIRST SERVICE AUGUST 2008!!!

Construction Pictures


Site work -
Aerial_2
March, 2007

Utilities
Aerial_2007-09-24
September, 2007

Foundation
Aerial_2007-10-25
October, 2007

Exterior walls
Aerial_2007-11-21
November, 2007

Roof trusses
Truss3
December, 2007

Front view
2007-12-08_1
December, 2007

Top view
2007-12-20_2
December, 2007

Top view
Aerial_2008-02-25
February, 2008

Steeple Installation
2008-02-26_53
February, 2008

Steeple Placement
2008-02-26_65
February, 2008

Finished Steeple
2008-02-26
February, 2008

Top view
2008-03-25
March, 2008


Front Scaffolding
2008-04-19
April, 2008

Front view
2008-05-07_31
May, 2008

Front view
2008-05-07_35
May, 2008

Side view
2008-05-07_38
May, 2008

Top view
2008-05-26
May, 2008

Top Rear view
.
June, 2008

Top view
2008-02-26
June, 2008

Top view
2008-02-26
June, 2008

Top view
2008-03-25
July, 2008

Top view
2008-03-25
July, 2008

Top view
2008-03-25
July, 2008


See more building pictures in the gallery.

 




Steeple Installation Video



home | contact us | site map

 

This page was last updated December 31 1969 19:00:00.

Google
WWW avalonchurch.org