Schedule
Submit Civil Drawing to Orange Cty: November, 2006
Submit Full Drawings to Orange Cty: December, 2006
Drawings returned from Orange Cty: April, 2007
Sitework to begin: January, 2007
Construction to begin: August, 2007
Electrical, Plumbing, HVAC completed by March, 2008
Interior framing, electrical, plumbing and HVAC rough-in: April, 2007
Exterior painting: April, 2008
Walls up and roof by April, 2007
Drywall, trim, interior doors, painting: June, 2007
Parking lot, sod and landscaping completed by July, 2008
FIRST SERVICE AUGUST 2008!!!
Construction Pictures
Site work -

March, 2007
Utilities

September, 2007
Foundation

October, 2007
Exterior walls

November, 2007
Roof trusses

December, 2007
Front view

December, 2007
Top view

December, 2007
Top view

February, 2008
Steeple Installation

February, 2008
Steeple Placement

February, 2008
Finished Steeple

February, 2008
Top view

March, 2008 |
Front Scaffolding

April, 2008
Front view

May, 2008
Front view

May, 2008
Side view

May, 2008
Top view

May, 2008
Top Rear view
. 
June, 2008
Top view

June, 2008
Top view

June, 2008
Top view

July, 2008
Top view

July, 2008
Top view

July, 2008 |
See more building pictures in the gallery.
|

Steeple Installation Video
|